Data Transfer
PROCESS REDESIGN
Analyzed and redesigned the existing ETL process
resulting in a 90% improvement in the run time
resulting in a 90% improvement in the run time
Our Client
- Source databases and Extract Transform and Load (ETL) process were poorly designed resulting in frequent stops and restarts requiring manual intervention and multi-shift monitoring of jobs.
- Key weekly and monthly SQL-based reports were taking too long to run (18-26 hours).
- Redundancy in data between data sources resulted in numerous errors and anomalous information.
Our Engagement
- Analyzed and redesigned the existing ETL process
- Streamlined the extract of data and reduced the redundancy of data
- Clarified data definitions and data sources to ensure the appropriate use of the data
- Improved performance of process for rebuilding cubes
- Cleaned-up error logs and underlying processes
Our Results
- Greatly improved speed of new ETL process runs for key weekly reports (2-4 hours a 90% improvement)
- Normalized databases with minimal data redundancies
- New process resulted in better data clarity and reduction in misunderstanding of the information produced